Building Eastern Europe's

green hydrogen future

The site of our new project
„Geo Restart Power Plant“

Project

The approach: constant electricity supply for production without downtimes

Project Dimensions
Phase I

RESOURCE AVAILABILITY

up to

600 MW

wind energy (Vestas V172 – 7.2 MW)

up to

400 MW

of energy storage

up to

45 000 T

H2 yearly production

up to

400 MW

solar energy (own plants & PPA)

up to

400 MW

electrolyzer capacity

up to

1000 T

H2 storage

7-7.5 m/s

windspeed at hub height

3000-3100 H/A

full load hours/year

1350-1450 H/A

full load hours/year

Location

favorable wind, solar and water resources

proximity to transport corridors via the Danube river from the Black Sea to the North Sea

proximity to existing and planned pipelines to Central Europe

Transporting hydrogen via a gas pipeline system
is the most cost-effective transportation solution

Existing gas infrastructure of Bulgaria is

in proximity
to the project

Retrofitting of the

existing gas transmission network

for H2 / natural gas blends 

Plans for

new dedicated H2 infrastructure

for transmission of pure hydrogen

Pipeline transport -> European hydrogen backbone

32

energy infrastructure operators enabling the development of a pan-European renewable and low-carbon hydrogen market

repurposing current pipeline

and newly built H2 infrastructure

Newly planned pipeline for

2030

will be constructed very close to proposed project site

Nevertheless, as we are aware of the challenges, we are open to other transport solutions

Liquefied H2 (LH2)

Ammonia (NH3) or Methanol (CH3OH)

Liquid Organic Hydrogen Carriers (LOHC)

Team

This is our second large-scale venture in the renewable energy sector

Our team has the proven expertise across the full project lifecycle

Dipl.-Ing. Thomas Funke

Investor Relations, Finance.

Architect, investor and visionary with a strong belief in renewable energy.

Initiator, owner and partner of multiple large-scale real estate and wind energy projects in Germany, Bulgaria and Poland.

Eng. Dimitar Hristov

Project Management

35+ years of experience in the construction and engineering industries.

For the past 20+ years, he has been the Managing Director of Geo Power Ltd., responsible for the development, construction and operation of several RES projects in Bulgaria.

Kamen Tcholov

Regulatory

25+ years of experience in the
legal industry.

For the past 20+ years, he has been Partner and Managing Partner of a leading law firm in Bulgaria and has a vast experience in the field of energy law with a focus on renewable energies, as well as in corporate and M&A deals structuring.

Dipl.-Ing. Rolf Engelbrecht-Schnür

Technology, Sales & Marketing

30+ years’ experience from the oil & gas and renewable energy sector for Shell, TenneT TSO and RePower AG.

Leading positions for international
big and medium-sized corporations from the solar, wind and geothermal energy sectors.

ADVISORS:

Prof. Dr. Pavel Zehtindzhiev

Leading Ornithologist with 80+ publications

Assoc. Prof. Yordan Yordanov

Geologist with 100+ scientific publications; Advisor to the Parliamentary Commission on Energy for 8 years

Prof. Markwart Kunz

Chemist, former member of the board of Südzucker AG
team-img1

370 000 MWh

produced in 2023

Equals the consumption of 200 000 households

Our previous venture continues to be the largest of its kind in Bulgaria

156 MW

installed capacity

52

Vestas V90 3.0 wind turbines

Investment:  € 270 000 000

           

Timeline

Project Geo Restart Power Plant

January 2023 – December 2028

Let’s build the green hydrogen future together! ​